The new fire access road on the south side of the Hartselle High School campus has been completed, according to project manager Jim Maynard.
The landscaping is the only thing that has not been completed. The widening of the front loop at the school is also in progress. Gravel has been poured and the loop will be paved before the start of the new school Monday.
Maynard added that the doors are currently being stained and the lockers are being installed in the athletic fieldhouse. The artificial turf will be installed this week and will continue into next week. The parking lot will also be paved later this week.